Project Timeline
Phase I
- Create a stone/granite planter around the existing Grange Hall/Town Hall message sign
- Determine bounds/markers for land owned by Town in area of work
- Talk with abutting property owner on West side as to SW marker and clearing "green space".
- Clean out "green space" area on West side
- Discuss phases of work with Heidi Marshall, Consulting Engineer
- Dialog with DOT
Phase II
- Continue dialog with Heidi Marshall and Dist. 5 (DOT)
- Obtain a "plan" from Heidi with conceptual sketches
- Have material to hand out, conceptual drawings for town meeting in March, 2016
Phase III
- Improve Memorial Park
- Install curbing around Park
- Update landscaping to included a Christmas tree Improve Parking lot area
- Replace existing stairs between upper and lower parking areas
- Install appropriate lighting for safety and aesthetics Landscape West and South sides of parking lot Crosswalk
- Provide a "paved" walkway on the North and South sides of Main Street with length to be determined by DOT and consulting engIneer
- Provide a pedestrian crosswalk to be determined by DOT and consulting engineer
- Create a grass/landscaped barrier "island" on South side with fencing/granite posts
Phase IV
- Repave complete parking lot and line all the parking spaces
- Any additional markings for handicapped parking, in/out directionals, etc.
- PLEASE NOTE THAT THE WORK UNDER EACH PHASE IS SUBJECT TO CHANGE, ADDITIONS, SUBTRACTIONS AND MOVEMENT AS TALKS WITH THE CONSULTING ENGINEER AND DOT CONTINUE.
- ENTRANCE and EXIT POINTS FOR THE PARKING LOT ARE STILL UNDER DISCUSSION AND CONSIDERATION AT THIS POINT.
Phase V
- Construction of gazebo in SW corner plantings of flowers/flower boxes
Revised draft Dec. 2015